Snap P2 first

Four walls only: P2, then P1, then the 14×6 bath. Confirm 7′-3″ east of F17 on the slab. Then cut P2. Furnace stays east of P2. Studs cut to 7′-7 1/2″ after you confirm the plate on the slab.

Weekend 10/4
Lumber list
  1. then
  2. then
  3. then
Partition9′-10″

P2

Storage west · 9′-10″

Snap P2 first — 7′-3″ east of F17. That is the hallway. Furnace stays east of this wall.

P2 · STORAGE WEST · 9′-10″ · 16″ OC · studs 7′-7 1/2″2-2x6 doorRO 3′-0″0″4′-0″8′-0″
  • Layout / end
  • King
  • Jack
  • PT bottom plate

Mark the paired plates from the start end

0″end
1′-4″X
2′-8″X
4′-0″X
5′-4″X
5′-8 1/4″king
5′-9 3/4″jack
6′-8″X
8′-0″X
8′-11 1/4″jack
9′-3/4″king
9′-4″X
9′-8 1/2″end
9′-10″end

Cut list

Wall 01 of 23 · Snap P2 first — 7′-3″ east of F17. That is the hallway. Furnace stays east of this wall.

CutPieceQtyCut
Bottom plate
PT 2×4 · PT on sill sealer. Splice over a stud.
19′-10″
Top plate
SPF 2×4 · Crown the same way as the cap.
19′-10″
Cap plate
SPF 2×4 · Goes on after the wall is up so you can lap corners.
19′-10″
Studs
SPF 2×4 · Floor-to-joist minus three plates. Cut from the shortest measurement.
97′-7 1/2″
King studs
SPF 2×4 · Full height, one each side of the RO. Mark K on the plate.
27′-7 1/2″
Jacks — door
SPF 2×4 · RO 3′-0″ × 6′-10″. Header sits on these.
26′-10″
Header — door
SPF 2×6 · 2-2x6, crown up, ½″ plywood spacer.
23′-0″
Head cripples — door
SPF 2×4 · Between header and top plate.
14″
Studs
13
7′-7 1/2″
Kings / jacks
2 / 2
PT plate
9.8 lf
On sill sealer
Tapcons
4
4′ OC into slab
  • doorRO 3′-0″ × 6′-10″ · 5′-11 1/4″ from start · 2-2x6Louvered 2/6 — combustion air for furnace and water heater

Stick-build this wall

  1. 1Confirm this wall on the slab: 9′-10″. Floor-to-joist 8′-0″. Cut studs 7′-7 1/2″ (shortest height minus three plates).
  2. 2Cut a matched pair of plates 9′-10″: pressure-treated bottom, SPF top. Crown the top the same way. Mark B / T and an arrow on the start end.
  3. 3Pair the plates and mark from the start end. Ends at 0″ and 9′-8 1/2″. kings at 5′-8 1/4″, 9′-3/4″. jacks at 5′-9 3/4″, 8′-11 1/4″. layout X at 1′-4″, 2′-8″, 4′-0″, 5′-4″, 6′-8″, 8′-0″, 9′-4″. far end 9′-10″..
  4. 4Door RO 3′-0″ × 6′-10″ at 5′-11 1/4″ from start. Kings at 5′-8 1/4″ and 9′-3/4″; jacks at 5′-9 3/4″ and 8′-11 1/4″. Header 2-2x6, crown up.
  5. 5Cut 11 full-height 2×4s at 7′-7 1/2″, 2 jacks, 1 cripples. Keep the offcuts — they become blocking.
  6. 6Tack the bottom plate to the chalk line with two Tapcons, 2″ in from each end. Do not cut the doorway out of the plate yet.
  7. 7Stick-build under the joists: stand both ends and any kings, then layout studs, then the first top plate. Toe-screw or nail as you go. You cannot tilt a full-height wall up in this basement.
  8. 8Plumb both faces. Fasten the remaining Tapcons — 4 total, 4′ OC. String the long walls before you call them done.
  9. 9Cap with the second top plate. Lap onto the neighboring walls. Slide ½″ drywall draftstop above the plate, tight to the joists.
  10. 10After the wall is plumbed and fastened, cut the bottom plate out of each doorway. Leave a clean RO.
  11. 11Louvered door or transfer grilles high and low. 30″ service clearance in front of the furnace.
  • Snap this first. 7′-3″ east of F17 — that line is the hallway, not storage.
  • Louvered door or transfer grilles high and low. 30″ service clearance in front of the furnace.
  • Furnace and water heater stay east of this wall.

Confirm 7′-3″ east of F17 on the slab. Then cut P2.