Materials

First drop

Weekend 1 is P2 first (the 7′-3″ wrap), then P1, then the 14×6 bath. Furring is a second trip. Prices are Midwest yard ballparks. Confirm every length on the slab. Studs cut to 7′-7 1/2″.

Weekend 1
$953

How you're framing it

Changing these rebuilds the list. Floor-to-joist is 8′-0″.

Studs
Cavity
Insulation
Furring
0 lf
Partitions
103 lf
Studs
126 pc
Wall area
825 sf

Yard ticket

Bring this to the desk

ItemQtyExt.
¼″ × 2-¾″ Tapcon, box of 75
Fasteners · 4′ OC, two at each plate end, 2″ in.
1 box$20
16d sinkers, 5 lb
Fasteners
1 box$18
3″ construction screws, 5 lb
Fasteners
2 box$43
Construction adhesive, 28 oz
Fasteners · Plates to slab.
3 tube$19
Fireblock foam, 12 oz
Insulation · Top-of-wall gaps, plumbing, electrical.
3 can$22
SPF 2×4, 10′
Lumber · Top + cap plates
2 pc$11
SPF 2×4, 12′
Lumber · Top + cap plates
8 pc$56
SPF 2×4, 16′
Lumber · Top + cap plates
4 pc$39
SPF 2×4, 8′
Lumber
133 pc$512
SPF 2×6, 8′
Lumber · 2-2x6 header · door
10 pc$69
PT 2×4, 10′
PT lumber · Bottom plates
1 pc$10
PT 2×4, 12′
PT lumber · Bottom plates
4 pc$50
PT 2×4, 16′
PT lumber · Bottom plates
2 pc$36
PT 2×4, 8′
PT lumber · Bottom plates
3 pc$22
Sill sealer, 50′ roll
Weather · Under every PT plate.
3 roll$25

Saw station

Grouped by length — check as you cut

CutCut toQtyBuy
15′-9″1pc16PT 2×4
15′-9″2pc16SPF 2×4
14′-0″1pc16PT 2×4
14′-0″2pc16SPF 2×4
11′-2″1pc12PT 2×4
11′-2″2pc12SPF 2×4
10′-9″1pc12PT 2×4
10′-9″2pc12SPF 2×4
10′-8″1pc12PT 2×4
10′-8″2pc12SPF 2×4
10′-6″1pc12PT 2×4
10′-6″2pc12SPF 2×4
9′-10″1pc10PT 2×4
9′-10″2pc10SPF 2×4
7′-7 1/2″99pc8SPF 2×4
7′-3″2pc8PT 2×4
7′-3″4pc8SPF 2×4
6′-10″10pc8SPF 2×4
6′-0″1pc8PT 2×4
6′-0″2pc8SPF 2×4
3′-0″4pc8SPF 2×6
2′-8″4pc8SPF 2×6
2′-4 3/4″2pc8SPF 2×6
4″5pc8SPF 2×4

Not on the weekend-1 ticket: drywall, mud, paint, doors, trim, LVT, EMT, devices, bath fixtures, the egress well, or tax. Electrical in this village is conduit — price that with the electrician. Interior partitions do not get XPS; that comes with the furring drop. Insulation is listed so you see the second trip — do not install it until the roughs pass.

Confirm 7′-3″ east of F17 on the slab. Then cut P2.

Snap P2